Belgian authorities have ordered Google to halt construction of a huge data centre near Charleroi, after inspectors found the company had nearly finished a 30,000-square-metre building even though the permit it depended on had been refused in August.

Inspectors from the Walloon Region visited the site at the Ecopôle business park in Aiseau-Presles, in the province of Hainaut, on Thursday 26 November. They found the building — covering three hectares, about the size of four football pitches — almost complete, with its structural shell closed. About 300 workers were on site when officials gave a verbal order to stop work.

Rows of computer servers inside a data centre
Server racks inside a data centre (file photo). Photo: BalticServers.com (CC BY-SA 3.0)

A permit refused over river water

The row is about a change Google wanted to make to a project that was already approved. In 2024 the company received a permit for three smaller data centre buildings, cooled by air, on the 53-hectare former mining site it bought in 2021. A year later Google asked to merge two of the buildings into one much larger one and to cool its servers with water drawn from the nearby River Sambre instead.

The Walloon administration approved that amendment in April 2026, but local residents appealed. In August, the Walloon minister responsible for spatial planning, François Desquesnes, rejected the revised permit, pointing to the data centre’s water needs after an exceptionally hot and dry summer. Google challenged that refusal before the Council of State, Belgium’s highest administrative court, with a public hearing set for 7 January 2027.

The minister’s office has stressed that the original 2024 permit remains valid, so Google may build under that permit — but not under the amended plans. The question now is whether the work already done matches the approved version or the refused one.

Greenpeace, drones and a report to prosecutors

The halt followed a campaign by Greenpeace Belgium, which used satellite images and drone footage to argue that construction had simply carried on after the permit was refused. On 23 November the environmental group filed an urgent request with the regional administration demanding the site be stopped immediately.

Regional officials went further on Friday 27 November. A spokesman, Nicolas Yernaux, told Agence France-Presse that a report alleging “a major offence” was being sent to public prosecutors — the illegal construction of a building covering three hectares. “That Google continues to build without a permit is disrespectful to the environment, local residents, and the law,” said Joeri Thijs, a spokesperson for Greenpeace Belgium.

Greenpeace links the project to Google’s water use at Saint-Ghislain, near Mons, where it says a comparable data centre pumps about one billion litres of water a year to cool its servers, returning only a quarter of it. Google has not yet responded publicly to the stop-work order.

The second Google site stopped in two months

The Belgian order is the second time in two months that a European government has stopped work at a Google data centre site. In Finland, a project in Muhos was suspended after the company was accused of illegally felling some 250,000 trees, and an investigation there is still ongoing.

The pattern reflects a wider backlash against the data centre boom. As tech giants race to build the computing capacity behind cloud services and artificial intelligence, local communities and regulators are pushing back over water, energy and land. Google has expanded its investment plans in Belgium to €5 billion over two years, but each new site now faces the same questions: how much water will it drink, and who gave it permission?

For now the Farciennes site is frozen. The Council of State will decide in January whether the minister was right to refuse the amended permit, and prosecutors will decide whether the near-finished building is a planning offence. Either way, the episode shows that even the world’s biggest tech company cannot simply build first and argue later. For more on the tech giants under pressure, see Nvidia reinstating Jensen Huang as chief executive after Trump’s intervention, Microsoft declaring Code Red after a 24-hour Exchange outage, and OpenAI counter-suing Apple over trade secrets.